EnTec Case Study: Stefani, Korinthos Solar Park Networking

Project Overview

EnTec undertook a significant project at the Stefani Solar Park in Korinthos to enhance its networking infrastructure. This project was crucial to support data transmission, CCTV, control room operations, and maintenance activities across the solar park. The primary focus was on planning and designing a robust fiber optics network, installing 8.5 kilometers of fiber optics, and ensuring end-to-end connectivity from the control room to the power station.

Project Objectives

The key objectives of this project were:

  1. Fiber Optics Network Planning and Design: Develop a comprehensive plan and design for the fiber optics network to ensure optimal data transmission and connectivity.
  2. Installation of 8.5 Km Fiber Optics: Implement a fiber optics network covering 8.5 kilometers to support various operational needs of the solar park.
  3. Joint Connections for Aerial and Ground-Running Networks: Establish reliable joints to connect aerial and ground-running fiber optics networks, ensuring seamless connectivity.
  4. Cabling Termination and Certification: Perform cabling termination and certification to guarantee the network’s reliability and performance.
  5. End-to-End Connection: Achieve a continuous and reliable connection from the control room to the power station to facilitate efficient operations.
  6. As-Built Report Production: Provide a detailed as-built report to document the network’s implementation and configuration.

Our Approach

To meet the project objectives, Praxis Factor implemented a strategic and meticulous approach:

  1. Planning and Design:
    • Conducted a thorough site survey to understand the specific requirements and challenges.
    • Designed a fiber optics network plan that optimized data transmission and connectivity across the solar park.
    • Developed a detailed project plan, outlining the installation process and timelines.
  2. Installation:
    • Expertly installed 8.5 kilometers of fiber optics, ensuring minimal disruption to ongoing operations.
    • Implemented joints to connect the aerial and ground-running fiber optics networks, providing robust and seamless connectivity.
    • Completed cabling termination with precision and conducted rigorous testing to certify the network’s performance.
  3. End-to-End Connection:
    • Established an uninterrupted connection from the control room to the power station, ensuring reliable data transmission and operational efficiency.
  4. Documentation:
    • Produced an as-built report detailing the network’s design, installation, and configuration for future reference and maintenance.

Impactful Outcomes

The successful implementation of this project resulted in several significant outcomes:

  1. Enhanced Operational Efficiency: The comprehensive fiber optics network improved data transmission, supporting efficient control room and maintenance operations.
  2. Robust Network Infrastructure: The reliable and seamless connection between the control room and power station enhanced the overall operational stability and performance of the solar park.
  3. Improved Security and Monitoring: The network’s support for CCTV operations ensured enhanced security and monitoring capabilities across the solar park.
  4. Future-Proof Design: The meticulous planning and robust installation provided a future-proof network infrastructure capable of supporting future expansions and technological advancements.

Contact Us

For more information on how Praxis Factor can help your organization achieve similar results, please contact us.

> Share

> You Might Also Like

Announcement: Praxis Factor and Shiji Group Partner for Infrasys Solutions

Praxis Factor partners with Shiji Group to bring the Marriott-certified Infrasys POS system to Greece and Cyprus. This collaboration aims to enhance hospitality services with advanced, cloud-based solutions, offering seamless integration, local support, and data-driven insights to optimize hotel operations and improve guest experiences.